Significant work underway to re-install windows

Take a look at the work underway at the Willowbranch Branch Library!

KBT Construction has been working hard to have all the wall prefabrication around the downstairs windows finished by Aug. 14.  The fiberglass reinforced panels that will be used to patch the ones that were removed will be delivered this weekend. The crew will work on Saturday to install them in order to have this area substantially completed by Aug. 21.  At that time, City of Jacksonville Public Works will review the progress.

Watch this blog for an update from Public Works following their review.